Current works across Campus Current works across Campus

Back

Colney Lane Pavillion Car Park works

Works will begin w/c Monday 25 November to facilitate the relocation of Norwich Rugby Club and redevelopment of the Colney Lane Pavillion.

The Colney Lane car park will be closed until Friday 28 February 2020.

We advise that visitors use the Triangle Car Park for alternative parking (please see bottom image).

Works will be undertaken by contractor MJS in two phases:

First phase: extension of the existing car park which will maintain pedestrian and cycle access via the existing Colney car park entrance wa.

Second phases – (date TBC) improvement works to highway. Pedestrian and cycle access will be diverted through the existing car park or utilise path diversion.

As part of these works, a temporary path (as indicated in the image below in purple) will be installed to ensure pedestrian and cycle access between UEA and the Norwich Research park.

The image below indicates the two phases of works.