New teaching rooms in ZICER

As part of the Summer Moves 2017 Project, work has commenced to convert existing offices on Level 0 of ZICER into six centrally bookable teaching rooms.

The programme of work is as follows:

1st Aug - site investigations within the building to establish ventilation details etc.
2nd Aug to 4th Aug - site setup including fencing of the site compound, erecting hoardings etc. The compound will be situated in the BMRC service road taking over 3 general (not disabled) parking bays.
7th Aug - construction works commence. There will be some noisy demolition work in the early stages of the project and also some drilling noise as partitions are put up.

The anticipated completion date for the works is 7th September.