Lift Replacement Project

This summer a programme of works will see the refurbishment of the following lifts on Campus:

  • Queen's Building Lift
  • Registry Lift
  • Estates Loading Bay Lift

A programme to repair the Queens Lift in a phased approach has already started as detailed in the timetable below.

Action

Date

Duration

Start phase 1

25/03/2019

2 weeks to complete repair and return lift to operation.

End of phase 1

08/04/19

*Handover delayed until 10/04/19

Lift will be in operation for approximately 4 weeks whilst awaiting parts before commencement of phase 2.

Start of phase 2 

13/05/2019

1 week to complete improvements. Note: lift out of action during this period.

End of phase 2

20/05/2019

 Lift returned to operation.

 

Works will commence on the Estates Loading Bay lift commencing Monday 17th June with a targeted completion date of Tuesday 27th August.

Works will commence on the Registry building lift commencing Monday 17th June with a targeted completion date of Monday 9th September.