Chancellors Drive roadworks

Starting Monday 28 October a programme of essential infrastructure works will begin on Chancellors Drive.

This will involve significant trenching works along Chancellors Drive which will last until March 2020.

Due to the width of multi-service trenching - which involves the installation of new drainage systems and additional connections to heating and electricity services - a single carriageway on Chancellors Drive will be closed at various points of the work.

Traffic management will be in place to control vehicle movements along Chancellors Drive and pedestrian diversions will be in place to manage the flow of campus users.

A detailed traffic management plan for weeks 1-4 is available here.

These works have been undertaken in a phased approach to enable Chancellors Drive to remain open for the duration of works.

As the trenching involves cutting into concrete these works are likely to generate noise disruption throughout.

This work will be carried out by contractor RG Carter and Breheny on behalf of the UEA Estates and Facilities Division.

Contractor compounds will be located behind the Security Lodge and BIOMASS yard.

Please note: the below dates and programme are subject to change.

PHASE 1 (Weeks 1-3)

COMMENCING 28 OCTOBER – 18 NOVEMBER

This will involve trenching to connect new drainage services. This will mean the closure of one carriageway of Chancellors Drive.

Traffic management will be in place to control vehicles movements with a four-way traffic light will be situated opposite the Chemistry Arch. Pedestrian access will be maintained but there will be diversions in place.

National Express bus services will continue to pick up on Chancellor's Drive and First Bus services will also continue.

PHASE 2 (Weeks 2-4)

COMMENCING 11 NOVEMBER – 25 NOVEMBER

This will involve further trenching to connect new drainage services and will mean the closure of one carriageway of Chancellors Drive between the Arts Post Room access road and Security Lodge zebra crossing. Trenching will also take place on the Estates boiler house roof.

Traffic management will be in place to control vehicles. Pedestrian access will be maintained but there will be diversions in place.

National Express bus services will continue to pick up on Chancellor's Drive and First Bus services will also continue.

PHASE 3 (Weeks 4 to 8)

COMMENCING 25 NOVEMBER – 27 DECEMBER

This will involve trenching on the Estates boiler house roof as well as trenching across the Chancellors Drive zebra crossing. This will mean the Chancellors Drive zebra crossing will not be in use.

As part of this phase a temporary crossing will be created across Chancellors Drive to the Security Lodge and there will be pedestrian diversions in place to direct foot traffic.

There will be further trenching on the footpath from Chancellors Drive to Founders Green and the Registry. This work will cause noise disruption to buildings in close proximity.

National Express bus services will continue to pick up on Chancellor's Drive and First Bus services will also continue.

PHASE 4 (Weeks 6 to 9)

COMMENCING 2 DECEMBER to 4 JANUARY

This will involve trenching from Waveney Road (near Dr Bike Repair Centre) to the University Drive drop off near Paston House to the BIOMASS yard.

PHASE 5 (Weeks 9 to 11)

COMMENCING 23 DECEMBER to 24 JANUARY

This will involve trenching across Chancellor’s Drive from the Estates Loading Bay to the ITCS building via the Chemistry Arch. This may involve the temporary closure of a single carriage. Traffic management plan to be confirmed at a later date.

Further trenching will be undertaken behind the Security Lodge and the contractor compound. This will mean no pedestrian access behind the Lodge to Chancellors Drive.

A diversion will be created across the Sportspark zebra crossing to manage flow of foot traffic in conjunction with a diversion on Cow Drive to direct foot traffic and cyclists via the INTO building onto University Drive.

As part of this phase, minor trenching between the Security Loading Bay at the Registry and University Drive will be carried out.

PHASE 6 (Weeks 12 to 16)

COMMENCING 27 JANUARY to 29 FEBRUARY

This will involve trenching from behind the Security Lodge along University Drive to level with the Sportspark. Further trenching will be undertaken from the Security Lodge zebra crossing across University Drive to the Main Car Park.

Traffic management plan to be confirmed but pedestrian diversions will be in place.

PHASE 7 (Weeks 12 to 16)

COMMENCING 24 FEBRUARY to 16 MARCH

This phase will involve trenching across University Drive by the Security Lodge into the Main Car Park.

Traffic management plan to be confirmed but pedestrian diversions will be in place.