Building 60 Vacated Spaces

Starting this September a series of works will be undertaken by MJS on behalf of the Estates and Facilities Division to re-purpose existing laboratory and office space in the Sciences building and Lawrence Stenhouse Building.

This follows completion and occupation of Building 60 by parts of the faculty of Science. The creation of further office space in the Sciences building for various University departments, including Student Services and ARM, is enabled by the vacation of areas in floor 1 and 3 of the Science building.

Due to the nature of refurbishment works, there will be some higher impact noisy works but these will be undertaken over a four week period between 9 September and 4 October. There will be further activities throughout causing intermittent noise and disruption to buildings users.

A further period of noisy works will be undertaken on floor 0 of the Sciences building for a four week period between 11 November and 6 December.

Targeted completion date for these works is 20 December.

Building/Location

Enabling Works

Start Date

Completion Date

Sciences

     

1.41

02/09/19

09/09/19

08/11/19

1.42

02/09/19

09/09/19

08/11/19

0.59/0.60/0.61/0.61a/0.61b/0.65

 

11/11/19

20/12/19

Lawrence Stenhouse Building

     

02.102

 

20/09/19

31/10/19

Chemistry

     

3.33

N/A

04/11/19

20/11/19