Current works across Campus Current works across Campus

Back

Library alterations

Internal alterations on Levels 01 & 02 of the Library to provide an additional 180 study spaces. The project commenced on Monday 19 June and involves the closure of LaRC and the installation of new rolling stack. The target completion date is 18 September.  The project also includes the full refurbishment of the two main Library lifts and the installation of a new ventilation plant, which has been completed. The work on levels 01 and 02 of the Library have also been completed. One passenger lift replacement is already installed. The second lift should be complete before Chritmas. This lift has been designed as a fire escape lift to help those people who have a mobility issue to escape from the building quickly and safely.